The situation
The garage existed, but the evidence needed for final certification did not sit in one place.
Obtaining retrospective approval was only part of the task. Before a final inspection certificate could be issued, the private certifier needed acceptable evidence for each relevant component of the completed work.
Following the final inspection, the private certifier issued a non-compliance notice requiring the outstanding certificates identified in the approval conditions. No single contractor could provide the complete package. Each requirement had to be assigned to the correct qualified person, investigated and documented in a form the certifier could assess.